The building’s structure, roof, and front canopy are now complete, and our focus is shifting to the front grounds.
In the next phase, crews will remove the existing sidewalks and begin installing a new sewer system. Once that work is finished, the new sidewalks will be poured.
We will also be installing new fencing near the bus drop-off area and creating a dedicated walkway for students who walk or ride the bus.
We are on track to complete all site work by mid-November, well before the first snowfall, allowing us to remove all temporary fencing. We’ll continue to share updates as the project moves forward and greatly appreciate your patience and support throughout the construction process.